![Navigation Bar [see links below]](images/leftnav2.gif) |
|
Restoration
Effort
II. Peirce Mill Restoration—The
Current Status
The restoration of Peirce Mill is well advanced. Work is
underway on repairs to the floors of the building, all the damaged machinery
has been removed, the machinery framework repaired, and an engineering study
of the water system has been completed. Details are as follows:
- Our contractor for the floor work, Historic Structures
Inc. (Steve Ortado and crew), have removed floorboards in the southwest
quadrant of the main floor and are repairing and re-installing damaged
or rotted floor joists. The work follows a detailed plan developed tby
our structural engineering consultants, Robert Silman Associates, to
deal with rotted joist ends where they enter pockets in the stone foundation
wall. The task is complex because the weight of the upper floors has
to be lifted section by section in order to be able to remove supporting
posts that rest on the floor boards and impede their removal. Work on
the remaining three quadrants of the mill floor will be carried out
during the latter half of 2007. The total cost of this work is estimated
at $50,000.
- As reported last year, our contractors for restoration
of the milling machinery, O'Rourke & Kiorpes, completed removal
of damaged gears and shafts inside the mill, and Rock Creek Park maintenance
staff worked with Steve Ortado to remove the damaged water wheel. O'Rourke
& Kiorpes are preparing to resume work in the summer of 2007 by
installing the new water wheel shaft and bearings. In 2008, they will
fabricate and install a new water wheel and new and repaired internal
gears and shafts, following engineering drawings prepared by our consulting
millwright, Derek Ogden. This work, the most expensive part of the restoration
project, will cost in excess of $300,000.
- A team of architects and engineers led by Bucher/Borges
Group has completed a conceptual design of a pumped water system to
power the water wheel. Rock Creek Park officials are currently reviewing
the concept. Once any requested changes to the concept are made, Bucher/Borges
will proceed to a detailed design and cost estimate of the system. As
depicted by photos in the most recent issue of our newsletter, Milling
About, it appears possible to make use of parts of an earlier installation
that functioned roughly 30 years ago - a pump pit beneath the flume
that draws water from the tailrace to recirculate it over the water
wheel. Depending on availability of funds, the installation of the system
could begin during 2007 and be completed in 2008. Estimated cost is
$230,000.
- Work being carried out by others, that is, work not
funded by the Friends, includes (1) correction of drainage problems
at the west side of the mill using funds granted to Rock Creek Park
by the DC Department of Transportation, and (2) maintenance costs funded
directly by Rock Creek Park, consisting of replacement of the mill roof
(completed January 2007), re-pointing of the stone foundation wall at
the basement level (completed April 2007),and restoration of windows
(on-going).
Our objective is to complete all these work elements by
the Fall of 2008 and to have the mill in operation shortly thereafter.
< Previous
| Next
>
Visit the
Mill | History
| Restoration | Fact Sheet
| Newsletter
Join Us | Links | Contact
Us | Home
|